The client could not close the office, so the floor was divided into three zones. Each zone was screened, fitted out and handed back before the next began, and all noisy work happened between six and nine in the morning.

Scope

Partitioning, acoustic treatment for two meeting rooms, false ceiling with concealed lighting, structured cabling, a server room with separate cooling, a pantry, and forty two workstations.

Result

Zero working days lost by the client. The final phase completed four days early, and the acoustic test in the meeting rooms passed on the first attempt.